Contracts & Change Orders

The paperwork that protects the margin. A contract is what you agreed to do and for how much — written from your own templates and signed online by the customer and by you. A change order is every time that agreement changes — recorded, priced, approved, and applied.

Quick overview

The one-sentence reason this module exists: on a fixed-price job, unrecorded extra work comes straight out of your profit. A change order turns "while you're here, could you also…" into a priced, approved, invoiceable line.

Both are admin-only, Plus plan.

Where to find it

Operations          (admin)
├── …
├── Contracts
│   └── Contract templates   (button at the top of the list)
└── Change Orders

You'll also see contracts on a project's Contracts tab, and a Change orders block — pending, oldest pending, approved value and schedule days — in the Financial section of the Dashboard.

Contracts

The register of your customer agreements, with a Contracts Total figure at the top and filters by status and project.

Creating a contract

FieldNotes
Contract numberAssigned automatically — CON plus ten digits — and unique within your company
CustomerWho it's with
ProjectThe job it covers. This is what links contract value to actual cost
Title & descriptionWhat the agreement is for
Start & end dateThe term
Amount + currencyThe contract value. Currency is a three-letter code — USD, BRL, EUR
Auto RenewWith a renewal type and notice period — see below
Contract templateOptional. Its text becomes this contract's document — see Contract templates. Your default template is pre-selected
Initial paymentOptional. Saving the contract creates an invoice for its amount, and an initial payment is recorded against that invoice

Statuses

StatusMeans
DraftBeing prepared
Pending ApprovalWith the customer or with your own approver
ActiveLive and in force
ExpiredRan past its end date
CancelledCalled off before it started or completed
TerminatedEnded early by one side

Row actions: View, Edit, Activate, Renew, Deactivate / Enable, Delete.

Signing moves the status for you: sending for signature takes a Draft to Pending Approval, and when both the customer and your company have signed, Jobmand fills in Signed Date and makes it Active. The one exception is a contract that couldn't be activated by hand either — an end date already in the past, or Auto Renew without a renewal type — which stays Pending Approval for you to fix.

Cancelled and Terminated contracts are locked. That's on purpose — a contract someone walked away from shouldn't be quietly editable afterwards. Cancelling also switches off any signing link that's still out. If the deal comes back, raise a new contract.

Auto renew

For maintenance agreements and retainers. Switch Auto Renew on, set the renewal type and the notice period.

Contracts approaching renewal show a Pending renew badge on the customer's Financial tab — your prompt to talk to them before it rolls over, or to give notice inside the window.

Contract templates

A template is your standard contract wording, written once and reused. Open Contracts → Contract templates.

GroupFields you can insert
CompanyName, address, phone, email, website
CustomerName, email, phone, address
ProjectName, address (the jobsite, or the customer's address if the project has none)
ContractNumber, title, amount, currency, start and end date, renewal type, notice period, contract date

Changing or deleting a template never touches contracts already created from it — each contract keeps its own copy of the text.

The samples are a starting point, not legal advice. Have your own wording reviewed before you send it to customers.

The contract document

Open a contract and go to the Document & Signature tab. The Contract document card holds the text the customer reads and signs.

Changing a sent contract resets the signing. Edit the text, amount, dates, customer or project after sending and the customer's link stops working and any company signature is cleared — send it again. Once the customer has signed, those changes are blocked until you Void signatures.

Sending for signature

Click Send for signature on the E-signature card.

OptionWhat it does
Email the signing link to the customerOn: Jobmand emails a Review & sign contract button with the PDF attached. Off: you just get the link, to share by text message, WhatsApp or however you like
EmailFilled in from the customer record; change it to send somewhere else
MessageAn optional note that appears in the email
Link valid for7 to 90 days. After that the link stops working

Either way, the next screen shows the signing link with a Copy button. If email isn't set up yet, or the message couldn't be delivered, it tells you so — copy the link and send it yourself.

The customer opens the link on any phone or computer, with no login. They read the contract, type their full legal name, draw or type their signature, tick the consent box and click Sign contract. Customers with portal access can also sign from the Contracts section of the portal.

The E-signature card tracks each step: sent (and to whom), opened, signed by the customer, countersigned by your company, fully signed.

Countersigning

Your company signs too. Click Countersign, confirm your name, draw or type your signature and sign. You can countersign before sending or after the customer signs — the order doesn't matter.

When both signatures are on the same version of the document the contract is Fully signed: the customer is emailed the signed PDF, Signed Date is filled in and the contract turns Active.

Void signatures clears every signature and link so the document can change again. It isn't available once the contract is fully signed — amend a signed contract with a change order.

The signed PDF & certificate

Download PDF always gives the current copy. Once anyone has signed it carries both signature blocks and a final Signature certificate page recording, for each signer: name, email, how they signed, when the link was sent and opened, when they signed, their IP address and their device.

The certificate also prints the document's fingerprint — a code calculated from the contract's content. Any change to that content produces a different fingerprint, which is how you show the signed text wasn't altered afterwards.

Electronic-signature rules vary by country and by type of agreement. Jobmand records the evidence; check with your legal advisor for contracts that need extra formalities.

Uploaded documents

The Contract Docs tab takes drag-and-dropped PDFs, Word or Excel files and images — up to 10 MB each — to download or delete later.

Use it for everything around the agreement: drawings, scope sheets, and the signed copy of any contract signed on paper or through another service. Contracts signed in Jobmand already have their signed PDF on the Document & Signature tab.

Invoices & payments

A contract is paid only through invoices, and Jobmand creates them for you:

The Invoices & payments card on the contract's Details tab lists them, each with its amount, what's been paid, the open balance and its status. To record money received, click Record Payment, choose the invoice it pays, and enter the amount, date, method and reference. The amount can't be more than that invoice's balance. The invoice moves to Partial or Paid on its own, and a contract with an open balance shows an Unpaid badge.

The same invoices appear in Invoices, and a payment recorded there shows up on the contract too.

Once a payment is recorded, the contract amount is fixed. To change what the customer owes after that, raise a change order. Before any payment, editing the amount simply updates the contract's invoice.

Change Orders

A change order records a change to an agreed project: extra work, reduced work, a delay, a revised completion date. Each one is anchored to a project and usually references a contract.

Why they matter

Three numbers on the admin dashboard come straight from here — Pending, Approved Value and Days Added. Together they answer the question that sinks fixed-price contractors: how much of what we're building did we actually agree to be paid for?

Raising a change order

FieldNotes
ProjectRequired — a change order always belongs to a job
Contract referenceWhich agreement it modifies
Change order numberSequential per project reads best: CO-01, CO-02
Date requestedWhen the customer asked
Description of changeBe specific. This is the text everyone argues over later
Cost impact + currencyCan be positive or negative — reduced scope is a change order too
Schedule / delay impactIn days, plus a delay reason
Affected tasks / milestonesWhat this actually touches
StatusStart at Draft, or go straight to Submitted

The approval workflow

Draft  →  Submitted  →  Approved  →  Completed
StageMeans
DraftYou're still pricing it
SubmittedSent for approval, waiting on a decision
ApprovedAgreed. The approver and approval date are recorded, along with the approved amount
CompletedThe extra work is done. The record locks

Move between stages with Change Status on the detail view.

Do not start the work at Draft. Approved is where the customer commits to the cost and the extra days. Work done before that is work you may not get paid for — which is the exact problem this module exists to prevent.

What approval changes

Approving a change order isn't just a status. Jobmand applies it:

Which is why the approved amount must be the number you'll actually invoice — it propagates.

Approvals & comments

Each change order carries an Approvals & Comments thread. Post a comment to record a conversation — a phone call where the client agreed, a note about why the price moved. When the disagreement arrives six months later, the thread is the record.

Customer approval

If the project is shared in the Customer Portal and customer approval is allowed for it, the client sees the change order in their Changes tab — number, cost impact, days, description, and the full approval history — with an Approve button.

Their approval is timestamped and attributed, which is a stronger record than an email saying "yes go ahead".

Documents & PDF export

Attach drawings, revised plans, site photos and meeting notes to the change order. Export PDF produces a single document on your company letterhead — the change, its cost and schedule impact, the approval block and its history — available at any status; it is the same document as D202 in Reports.

Common workflows

Set up your contract templates (once)

  1. Contracts → Contract templates → New template
  2. Start from a sample…, or paste your existing contract wording
  3. Replace names, amounts and dates with fields using Insert field
  4. Tick Pre-select for new contracts on the one you use most, and Save template
  5. Have the wording reviewed before the first contract goes out

Set up and sign a contract for a new job

  1. Create the project first
  2. Contracts → New Contract — customer, project, title, term, amount, and a contract template
  3. Open the contract → Document & Signature, read the text and Save document if you changed it
  4. Send for signature — by email, or copy the link and send it your way
  5. Countersign for your company, before or after the customer
  6. When both have signed the contract turns Active and the customer gets the signed PDF
  7. If it's a recurring agreement, switch on Auto Renew with the right notice period

Handle "while you're here, could you also…"

  1. Change Orders → new, against that project
  2. Write the description of change specifically — what's in, what's out
  3. Price the cost impact and estimate the days honestly
  4. Set status to Submitted and send it to the client (portal, or Export PDF by email)
  5. Do not start the work yet
  6. On agreement, set Approved with the approved amount — contract, project value and completion date update
  7. Do the work, then set Completed and invoice it

Monthly change-order review

  1. Dashboard — read the change-order strip: Pending, Approved, Approved Value, Days Added
  2. Open Change Orders, filter to Submitted — anything sitting there is work at risk
  3. Chase each one; a submitted change order nobody chases becomes free work
  4. Check Days Added against your schedule promises

Renew a maintenance contract

  1. Watch for the Pending renew badge on the customer's Financial tab
  2. Decide before the notice period closes
  3. To continue: Renew, adjusting the amount if the price has moved
  4. To stop: give notice inside the window and set the contract to the appropriate end state

FAQ & Troubleshooting

Can I edit a Cancelled or Terminated contract?
No, they're locked. Raise a new contract if the work restarts.
The customer says they never got the signing email.
Check the address shown on the E-signature card and ask them to look in spam. If the send screen said email isn't set up or couldn't be delivered, nothing was sent — use Resend with the email box unticked and send them the link yourself.
The customer opens the link and it says it's no longer valid.
The link expired, was replaced by a newer one, was switched off, or the contract changed or was cancelled after sending. Send it again.
I need to change a contract the customer already signed.
If only the customer has signed: Void signatures, make the change, and send it again. If both of you have signed, the contract is final — record the change with a change order.
Why does Countersign ask me to sign again?
The document changed after you signed, so your signature was for an earlier version. Countersign the current one.
Is a typed signature as good as a drawn one?
Both are recorded the same way — name, time, IP address, device and consent — and the certificate says which method was used.
Both parties signed but the contract didn't turn Active.
It stays Pending Approval when a manual activation would also be refused — usually an end date in the past, or Auto Renew switched on without a renewal type or notice period. Fix that and click Activate.
Can two contracts have the same number?
Not within your company — each number is unique. Numbering is per company, so another company on Jobmand can have its own CON0000000001.
A change order was approved but the project budget didn't change.
Check the approved amount is filled in and that the change order references the right project and contract. The value propagates from those fields.
Can a change order reduce the price?
Yes — enter a negative cost impact. Descoping is a change to the agreement just as much as adding work is.
Can I edit a Completed change order?
No. Completed locks the record. If something was wrong, raise a corrective change order that references it.
The customer approved by email. Do I still need a change order?
Yes. Raise it, attach the email under Documents, and approve it. The change order is what actually updates the contract, the project value and the schedule.
My customer can't see the Approve button in the portal.
Customer approval has to be allowed for that project, and they can't approve something they've already approved. Check the project's portal settings.
Can I record a payment on a contract without an invoice?
No. A contract is paid only through its invoices, so every payment names one. If a contract has no invoice yet, give it an amount: saving creates the invoice.
Days Added on the dashboard looks huge.
It's the sum of schedule impact across all approved change orders. A big number means your delivery dates have moved a long way from what you originally sold — worth a conversation with the customers affected.
Do I need a contract to raise a change order?
A project is required; a contract reference is strongly recommended. Without one, there's no agreement for the approved value to update.